Client
Bristol-Myers Squibb
Construction Manager
Como
Requirement
Installation of partitioning and ceiling packages to occupied building
Duration
36 weeks
Project development
Bristol-Myers Squibb is a global biopharmaceutical company, headquartered in New York. BOK was appointed to deliver building services to the UK head office in Middlesex. Installation of dry wall partitioning and suspended ceiling packages were conducted while the building was fully occupied. Works to three floors was completed over five phases, resulting in the refurbishment of the entire building.
BOK's team of 15 skilled trades professionals transformed the space to a very high standard, with great attention to detail. Among the distinctive features constructed were curved partitioning and premium timber feature ceilings to meeting rooms and work spaces.
Testimonials
BOK Group services provided
- Dry wall partitioning
- Suspended ceilings
- Carpentry and joinery
- Plastering, tape and jointing